Project Timeline
The current scheme was granted outline planning permission in December 2010. This is an indicative timeline for the remaining work needed.
Actual timings will depend upon the consultation and planning process and future demand for facilities planned on the site.
| Summer 2011 | Develop community consultation strategy for Phase 1 with community groups and volunteers |
| Autumn 2011 / Spring 2012 | Detailed design work Phase 1 Submission of reserved matters applications Phase 1 |
| 2012 | Start of construction work Phase 1 |
| 2016/17 | Estimated completion of development |